Key takeaways
Lien rights are the remedies an unpaid contractor, subcontractor or supplier holds on a construction project, and which one you have depends on the project. Private work gives a lien against the property; public work gives no lien at all, only a claim against the payment bond.
The phrase is used loosely and it covers a bundle rather than one thing. On a construction project, a party who has supplied labour, materials or equipment and has not been paid may hold one or more of:
The delivered mechanics lien page covers the first of these in depth: how it attaches, how it is enforced, what it does to a property. This page answers the question that comes before that one, which is which remedy you have at all.
Before anything else, establish what kind of project it is. Three categories, three different answers.
Project type | Primary remedy | Governing framework |
|---|---|---|
Private | Mechanics lien against the property, plus a bond claim if the job is bonded | State mechanics lien statutes |
State, county or municipal public | Claim against the contractor's payment bond. No lien | State "Little Miller Act" statutes |
Federal | Claim against the Miller Act payment bond. No lien | Federal statute, 40 U.S.C. 3131 and following |
Suppliers get this wrong in a specific and expensive way: they treat a public job like a private one, let the bond claim deadlines pass while preparing to file a lien, and then discover there is nothing to file against. The information needed to avoid it is available at quoting, which is the argument at the end of this page.
On private work the lien attaches to the improved property, which gives it its force: the owner cannot sell or refinance cleanly with a lien on title, so there is pressure to resolve it even where the owner has already paid the contractor.
That force is the reason the statutes impose conditions. Most states require a preliminary notice early in the job, then a filing within a set period after last furnishing or completion, then an action to enforce within another. California's rule is representative of the first step: under Civil Code section 8204, a preliminary notice must be given not later than 20 days after the claimant first furnished work, and a late notice limits the claim to work performed in the 20 days before service and anything after.
The preliminary notice page covers that step across states. The point to carry here is that on private work the remedy exists but is conditional, and the condition usually falls due in the first weeks of the job, long before anyone is late paying.
Public property cannot be sold to satisfy a private claim, so mechanics lien statutes do not reach it. Congress and the states solved the resulting gap the same way: by requiring the prime contractor to post a payment bond, and giving those below it a claim against the surety.
On federal work that is the Miller Act. The deadlines under 40 U.S.C. 3133 are specific and worth memorising if you sell into federal jobs. A claimant with a direct contractual relationship with a subcontractor but not with the prime contractor must give written notice to the prime within 90 days from the date on which it last performed labour or supplied material, stating the amount claimed and identifying the party it supplied with substantial accuracy. Any civil action must be brought no later than one year after the day the last labour was performed or material supplied.
Two things follow. Both clocks run from your last day on the job rather than from the invoice or from the day payment became late, which means the clock is usually already running while you are still expecting to be paid normally. And the 90-day notice is a precondition: satisfying the one-year deadline does not help if the notice was never given.
State and local public work runs on each state's own version, commonly called a Little Miller Act. The structure is similar and the deadlines are not, so do not carry federal timings onto a state job or the reverse.
Rights do not extend indefinitely. A general contractor, its subcontractors, and the suppliers to those subcontractors are almost always covered. Below that the picture varies sharply, and a supplier to a supplier frequently has no lien or bond claim at all in a given state.
This matters more than it sounds, because a distributor may not know which tier it occupies. Selling to a company that turns out to be a materials supplier rather than a subcontractor can put you a tier further down than you assumed, and the question is answered by what your customer does on that job rather than by what it usually does.
Equipment lessors and design professionals are covered in many states and not all. If either describes your business, the entitlement question is worth settling once with counsel rather than per project.
Entitlement comes from furnishing to the project. Keeping the right comes from procedure, and the procedure is the part that fails.
Every one of these is knowable on the first day of the job. None of them depends on whether the customer looks like a payment risk, which is why treating them as a response to trouble is the wrong model.
A missed deadline. The most common, and usually the notice rather than the filing, because the notice falls due while everything still looks fine.
A waiver signed for more than was received. A lien waiver given in exchange for a payment that has not cleared, or an unconditional waiver where a conditional one was appropriate, gives up the remedy for amounts you may never see.
An endorsed joint check with no allocation agreement. In many states endorsing presumes payment in full of what was owed at that date. The joint check agreement page covers why the written agreement is what prevents that.
Being the wrong tier. Not a mistake so much as a fact, and the reason to establish your position on the chain at the start rather than at the end.
A fifth deserves mention because it is contractual rather than procedural: some subcontracts contain a prospective waiver of lien rights. Several states prohibit or restrict those, and several do not. Read the subcontract before signing rather than assuming the statute protects you.
The practical answer is that all of this is decided by information collected at the start, and the collection is the hard part rather than the law.
Ask for the project type, the owner, the prime contractor, the site address and whether the job is bonded, as required fields when a construction customer opens an account or starts a job, in the same way the note on trade credit in building materials argues for collecting the rest of the application properly. Then diary the notice and claim deadlines for that project type at the moment of first delivery.
It is also worth being honest about what this changes commercially. A supplier that reliably preserves its remedies can extend more credit on a given job than one that does not, because the downside is bounded differently. That belongs in the credit risk assessment on construction customers, and it is a reason to treat notice discipline as a credit function rather than as administration. Where the exposure is in equipment rather than project work, a UCC-1 financing statement is the parallel tool, and retainage is the balance most likely to still be outstanding when the remedies matter.
This page is general information rather than legal advice. Deadlines, tier cut-offs and waiver rules vary by state and by project, and a specific claim belongs with construction counsel in that state.
No. Public property cannot be sold to satisfy a private claim, so mechanics lien statutes do not reach it. The substitute is a claim against the payment bond the prime contractor was required to post, which runs on its own deadlines and is not a lien at all.
Under the Miller Act, a claimant with a contract with a subcontractor rather than the prime must give written notice to the prime within 90 days of last furnishing labour or material, and any action must be brought no later than one year after that last day.
Generally anyone who improved the property: contractors, subcontractors, labourers, material suppliers and often equipment lessors and design professionals. Rights usually stop somewhere down the chain, and a supplier to a supplier frequently has none. The cut-off is set by state law.
The entitlement arises from furnishing to the project, but keeping it almost always depends on procedure. Most states require a preliminary notice within days of first furnishing, then a filing within another deadline. Miss either and the right is reduced or gone.
Four common ways: missing a notice or filing deadline, signing a lien waiver for more than you received, endorsing a joint check with no allocation agreement, or being a tier too far down the chain to qualify in that state.
A mechanics lien is one of the remedies. Lien rights is the broader term for whatever you hold on a given project, which may be a lien, a bond claim, a stop payment notice, or a prompt payment claim, depending on the project and your position in the chain.